Basic information of project:
Time: 2020-2021
Location: China
Type: Plaza,Office Building and High-rise residential building.
Project name: Firedoor and entrance door project case of Nanning Ronghe-Linxi Mansion 7-4 North Block House
Project Address: Dongan Road, Qingxiu District, Nanning City, Guangxi, China
Project introduction:
The item located on an important traffic road, with an area of 50000 ㎡, is an important item that is prioritized and valued by the government. Construction items include shopping supermarkets, real estate buildings, schools, hospitals, amusement parks, parks and high-class apartment buildings. The category promises to bring a modern comfortable life to people. In addition, the item with a large investment capital from China's major real estate corporations, with strict requirements and quality control, promises to be a new breakthrough item in the real estate industry.
Project Challenge and solution:
In this project, we supplied 33 sets steel entrance front door,74 fire door
and finished size measurement, production, delivery, installation and testing.
Although this project consists of many difficulties, such as scattered project distribution, poor on-site construction equipment, narrow transportation roads, and multiple projects constructed at the same time, centralized delivery, large quantities and urgent construction period.
Solution:
1. Urgently dispatch the project management resources, complete the on-site product quantity, specification and configuration statistics, and specify the node schedule. Only the production line resources can be analyzed through zunle operation management system to automatically complete the accurate production scheduling
2. Give full play to the manufacturing and design characteristics of zunle Zhineng, strive to produce and ensure 100% self built and qualified warehousing
3. Realize seamless production line through intelligent logistics system and deliver goods overnight
4.Through the data decision-making system, dispatch four installation teams to carry out simultaneous linkage construction, cross and go through multiple processes, and complete the installation and construction of departmental products as far as possible
With a high sense of responsibility, Zonle has successfully completed the work item and received high appreciation from the contractor.