Basic information of the project:
Project name: Wooden door project case of Nanning Wanke Fifth Park Phase I
Time: 2020
Location: China
Floor space:70000.00 square meters
Type: ordinary residence, high-grade residence, foreign building
Project Address: 16 Kunling Road, Xingning District, Nanning Guangxi, China
House type:88~138square meters
Project introduction:
Wanke Fifth Park is the primary product of Guangxi Vanke high-end improvement department and the fourth fifth park in China. Located in the north of Nanning East Railway Station, at the intersection of Kunling Road and Nakuang Road,it is a low-density ecological high-end residential area focused on by the government.The natural landscape resources around the project are rich, surrounded by eight size parks, and surrounded by the Nakao River water system in the north. The project has developed traffic network and is close to the extension line of Metro Line 5. After the opening of Hepo Road, it will direct to Fengling.
There is a kindergarten to a senior high school in the neighborhood, enjoying full-age supporting education and international high-end health care and medical resources. And is equipped with large commercial body, such as Xincheng Wuyue square, Outlets, conducted five through landscape resources unique, have had been inspected by state leaders that take an examination of river wetland park, surrounded by around 8 wetland park, near the hot spring valley, river bay hot spring resort, rural world four national 4 a level scenic area, north drainage project ring waist, Form an ecological habitable zone.
Project Challenge and solution:
1. Scattered projects
2. The size of the hole is not uniform
3. The site construction equipment is simple and the transportation road is narrow
4. Simultaneous construction of multiple projects
5. Centralized delivery, large amount of engineering, tight schedule
Solution:
Due to the complexity of the reconstruction project, the preliminary construction progress is slow. From May to October 2021, only 4073 doors will be delivered, and about 3000 doors will be delivered at the end of the year. The delivery pressure is unprecedented and almost impossible to complete. After repeated discussions and consultations with Vanke, Zonle Door set up Vanke project operation scheduling command center. Combined with Zonle Door's comprehensive operation advantages, the whole chain of raw material supply chain, production, logistics and transportation, and on-site construction was fully opened, forming the highest priority full chain response plan.